There’s been quite a bit of progress in the past couple of weeks. Windows are in and the siding has been repaired. What do you think of the new 3rd floor window?
The gas fireplace also went in last week. The original plan was to keep the center chimney and fit a unit inside of it, but getting the space back on the third floor bedroom drove us to put a whole new unit in.
And finally the basement windows have been replaced. They are so much better than the drafty old windows that used to be there. In fact they were so ugly I don’t think we have any pictures of them!
So next the HVAC, plumbing and electrical are to go in and then we can start the finishing phase!







The wonderful Town of Needham has decided to reject our applications for permits a second time because there “wasn’t enough detail” in the architects plans. So we’ve started to take our frustration out on the poor house…. demo time!